The Royal Society of Medicine has worked closely with professional advisors to draw up architects' plans and to work through the relevant costings. The financial estimate for the Phase 2 construction work is approximately £1.9 million.
Phase 1 - COMPLETED
| Training suite and three seminar rooms | £308,000 |
| Private Dining Room | £277,000 |
Phase 2: |
| New lecture theatre | £966,000 |
| First floor meeting rooms | £421,000 |
| New washrooms | £66,000 |
| Professional fees @ 22% | £197,000 |
| Contingency 10% | £165,000 |
| Sub-total | £1,815,000 |
| Payable VAT | £90,750 |
| Total required | £1.906 million |